POLLUTION PIPELINE: AUSTRALIA’S DIRTIEST DATA CENTRES

Australians are building a cleaner grid as our ageing coal power stations retire. Renewables and storage now supply more than 45% of electricity in our main grid, nearly double their share six years ago, and gas generation is dropping to record lows (Open Electricity 2026). Households are leading the charge through rooftop solar and home batteries. That shift is cutting climate pollution, reducing wholesale power prices and better protecting communities from worsening fires, floods and extreme heat.

The data centre boom has arrived at a critical point in that shift. There are 225 data centres lined up to connect to the main grid, more than double the number a year ago. Within a decade the Australian Energy Market Operator (AEMO) forecasts this industry could use as much electricity as nearly all the homes in New South Wales and Victoria combined. The risks for our clean energy switch, power bills and climate pollution are significant.

Our analysis of the largest data centre proposals in Australia reveals those that threaten to pollute the most are planned for New South Wales, Victoria, Queensland and the Northern Territory. If they don’t bring new renewables and storage to match their demand – or worse, build dedicated gas generation instead of renewables – together they could add 39.7 million tonnes of climate pollution a year by 2035, almost as much as Australia’s three most polluting coal power stations combined.

None of this is inevitable. If data centres are required to bring new renewables and storage to match their demand as soon as possible, their growth could help build Australia’s clean energy supply instead of extending our use of polluting coal and gas, and driving up power prices.


Key Findings

  • If all nine are built they could use more than 50 terawatt hours of power from the grid a year by 2035 – over two-thirds of what all homes in Australia use today.
  • If that demand isn’t matched by extra solar, wind and storage it could add 39.7 million tonnes of climate pollution a year by 2035; or almost as much pollution as our three dirtiest coal power stations emit today: Loy Yang A, Eraring and Bayswater.
  • In Victoria, three data centre proposals together risk adding 17.7 million tonnes of pollution a year – more than Australia’s most polluting coal power station, Loy Yang A.
  • In New South Wales, four proposals could together add 10.2 million tonnes a year, more than 1.5 times as much as the Vales Point coalfired power station.
  • In Queensland, the Western Downs data centre proposal alone could add 8.3 million tonnes a year; more than Stanwell coal power station.
  • Modelling consistently shows that without new renewables and storage to match demand, data centres push up power prices. Baringa modelled a 20% rise in average wholesale prices across the main grid by 2035.
  • Generation alone isn’t enough. Data centres run around the clock, so they also need new storage from day one, or homes and businesses foot the bill.
  • Industry could be priced out, too. Tomago, Australia’s largest energy user, needed $2.5 billion in government support for high energy costs, and data centres with deep pockets could outbid industries like it when their power contracts end.
  • Sydney Water forecasts data centres could take 15-20% of Sydney’s water supply by 2035, in a city that has spent almost half the past 20 years in drought.
  • Demand in Melbourne is also surging, with water storage levels there sitting 20% lower than the same time two years ago as climate change drives lower cool season rainfall in south-east Australia.
  • Like coal, gas is a harmful fossil fuel that’s highly polluting wherever it’s extracted, processed and burned. Building new gas power stations would lock in decades of pollution that fuels worsening heat, drought, fire and floods.
  • It’s also a poor use of our gas, since data centres can run on solar and wind. Since east coast exports began in 2015, gas prices have roughly doubled and put manufacturers that still rely on gas under pressure.
  • For gas companies, data centres offer a large, long-term customer to help justify new, polluting gas projects exactly as domestic demand for gas elsewhere is falling.
  • In fact, several data centre developers – including some with ties to the gas industry – want to build their own gas power stations:
    • Beetaloo Digital (Northern Territory), a subsidiary of gas company Beetaloo Energy, plans up to two gigawatts (GW) to create demand for its own fracked gas.
    • Project Meridien (Western Australia) proposes 1.5 GW, about twice the size of the biggest gas power station running today. One backer owns a company that has sought to frack the Kimberley.
    • Project Ares (Northern Territory) would initially run off a one GW gas power station, and even with its solar and battery running could burn more gas each day than all the Territory’s homes and businesses use on average.
  • The United States is a warning: 181 GW of new gas generation is being proposed alongside data centres globally, and more than 90% of that is within the US. Gas built while developers wait for grid connection risk being permanent.
  • Matching data centre demand with new renewables and storage would largely neutralise the extra climate pollution and price risks.
  • Renewables and storage already supply more than 45% of Australia’s main grid, or nearly double six years ago.
  • Another 43.6 gigawatts of approved renewable projects are awaiting buyers, more than enough for forecast data centre growth. More than 233 GW hours of big batteries are also moving through planning and construction.
  • Before data centres switch on, they should sign long-term contracts to buy power from wind, solar and battery projects that aren’t yet funded.
  • Large-scale solar projects have taken 21 months on average to build once funded, and wind projects about 30 months. That means data centres can have new renewables and storage running within three years of connecting to the grid.
  • Some of the proposals are already moving through planning, and new ones keep arriving: 225 data centres are now lined up to connect to the main grid, more than double a year ago.
  • Not all will go ahead, but those approved in the next few years will still be running in decades. Unless standards cover each one as it plans energy supply and starts operating, the industry will lock in climate harm that readily available renewable energy would avoid.
  • At a minimum, standards must cover every data centre over 30 megawatts that starts operating after the Federal Government set out its expectations in March 2026.
  • They should require data centres to match demand with new renewable sources within three years, rule out gas as a main power source, and limit water use.
  • Many of these companies already buy renewables, but it’s voluntary and results in certificates not new projects. Strong standards can deliver the new clean energy we need, instead of dragging us back.