Dirty Data
Centre Watch
Australia is in the midst of a critical clean energy switch and data centre boom.
We’ve crunched the numbers for some of the most polluting data centre proposals in Australia. The scale is bonkers, so we made this to show you what’s at stake.
So what’s that got to do with your fridge?
Let’s start small
One fridge humming away all year
Plugged into Australia’s grid, the average fridge creates about 0.22 tonnes of climate pollution a year.
0.22 tonnes
of climate pollution a year
So, how polluting is one data centre?
Pollution from one large data centre connected to the grid =
38 million fridges non‑stop
Hard to imagine, but that’s more than 2× the pollution that every fridge in every Australian home would emit running non-stop for a whole year.
38,136,917
Fridges running for a year
One bad data centre
3.1 million cars driving all year
That’s one in every five cars on Australia’s roads, driving for a whole year.
3,071,871
Cars on the road for a year
Or, pollution from one large data centre connected to the grid =
74,800 heavy trucks on the road
That’s 70% of all articulated trucks in Australia, hauling freight all year long.
74,775
Heavy trucks on the road for a year
Or, pollution from one large data centre connected to the grid =
Vanuatu 16 times over
It would take the entire nation of Vanuatu 16 years to emit the same amount of climate pollution as a single data centre.
16×
Vanuatu’s annual climate pollution
One large data centre connected to the grid
Introducing Western Downs Digital Park
Without bringing on new renewables and storage to match its demand, this one data centre would produce 8.3 million tonnes of CO₂. The proposal is the biggest in the country, with a total maximum power demand of 3.24 GW (IT capacity of 2.16 GW).
Even running at just 50% of its full capacity, that translates to 3.1 million cars, or 38 million fridges, or 75,000 heavy trucks or 16× Vanuatu’s entire emissions.
8,300,000
Tonnes of climate pollution (CO₂)
Australia’s most polluting proposals
Western Downs is one of nine proposals
We list the nine most polluting data centre proposals across the country. Not all of these proposals might go ahead. But if they do go ahead as currently proposed, the nine most polluting could collectively emit:
And there are at least 215 other data centres proposed across the country.
39,700,000
Tonnes of climate pollution every single year
- 16× Vanuatu
- 74.8K trucks
- 3.1M cars
- 38.1M fridges
Australia’s most polluting proposals currently in the pipeline
Learn more about the most polluting data centre proposals
Ranked by the climate pollution each would create every year, if powered as proposed in publicly available documentation. Tap a project to see the details.
-
Rank 1 Western Downs Digital Park Climate pollution: 8.3 Mt/yr Same as 3.1M cars
Dalby, Queensland
Western Downs Digital Park
The project: The Western Downs Digital Park – a proposal by Zerra DC – is the biggest in the country, and is located in a major gas extraction and generation region. AI company Anthropic has signed a lease for the first stage, targeting operation from 2027. The project is progressing through the planning assessment process.
Energy: IT load of 2.16 GW, with maximum power demand of 3.24 gigawatts (GW) across four buildings, including the power needed for cooling and other operations. Planning documents show it connecting to the national electricity grid, but Zerra DC has not ruled out building dedicated on-site gas generation. It also plans to install a battery (HDR 2026).
Water: The Dalby community has concerns around the facility’s water use, as the gas extraction industry is already impacting this region’s water sources (Whiteman 2026). The developer indicates it intends to primarily use air-cooling technology at the facility, rather than water. However, the facility could still use more than 30 million litres of water a year in total (based on 21,000 litres of water use each day per its four buildings). It is considering on-site supply options including rainwater harvesting and treated wastewater, and says it will not draw from the town water supply (HDR 2026).
Location
Dalby, Queensland
Site details
- Developer
- Zerra DC
- Customer
- Anthropic (first stage)
- Status
- Planning assessment
- Total capacity
- 3,240 MW
- Actual utilisation
- 1,620 MW
- Energy source
- Grid
Climate pollution
8.3 Mt CO₂-e / yr
That’s like 3.1 million cars on the road for a whole year.
Share of 2035 target
4.5%
From one project, every year connected to the grid.
-
Rank 2 Victorian AI Hub Climate pollution: 7.0 Mt/yr Same as 2.6M cars
Plumpton, Victoria
Victorian AI Hub
The project: The Victorian AI Hub, proposed by Syncline, is still in early development. It would cover a 350-hectare site beside the Melbourne Renewable Energy Hub in Plumpton.
Energy: The project includes four large data centres connected to the grid, with a maximum power demand of 2.4 GW. Syncline had planned to install gas turbines at the site, but has recently indicated that it no longer intends to do so in response to community feedback. It is also considering a mix of investment in new renewable generation and power from the grid, though no firm commitments have been made (Senate Environment and Communications References Committee 2026).
Water: Syncline plans to use recycled water at the facility (White 2026).
Location
Plumpton, Victoria
Site details
- Developer
- Syncline
- Customer
- To come
- Status
- Early development
- Total capacity
- 2,400 MW
- Actual utilisation
- 1,200 MW
- Energy source
- Grid
Climate pollution
7.0 Mt CO₂-e / yr
That’s like 2.6 million cars on the road for a whole year.
Share of 2035 target
3.8%
From one project, every year connected to the grid.
-
Rank 3 Yallourn Energy Security Precinct Climate pollution: 5.8 Mt/yr Same as 2.2M cars
Latrobe Valley, Victoria
Yallourn Energy Security Precinct
The project: EnergyAustralia is looking to develop its Yallourn coal power station site, due to close in mid-2028, into a new precinct, including two data centres each up to 1 GW.
Energy: The precinct would include up to 300 MW of gas generation and up to 2.7 GW of battery storage (EnergyAustralia 2026).
Water: Energy Australia has not outlined any plans to minimise water use at the site.
Location
Latrobe Valley, Victoria
Site details
- Developer
- EnergyAustralia
- Customer
- To come
- Status
- Early development
- Total capacity
- 2,000 MW
- Actual utilisation
- 1,000 MW
- Energy source
- Grid; gas for firming
Climate pollution
5.8 Mt CO₂-e / yr
That’s like 2.2 million cars on the road for a whole year.
Share of 2035 target
3.2%
From one project, every year connected to the grid.
-
Rank 4 M5 Data Centre Climate pollution: 4.9 Mt/yr Same as 1.8M cars
Geelong, Victoria
M5 Data Centre
The project: NEXTDC has acquired a site in the north of Geelong targeting 1.2 GW of IT capacity, with design and town planning underway (NEXTDC 2026).
Energy: No commitments have been made in relation to energy.
Water: No commitments have been made in relation to water use.
Location
Geelong, Victoria
Site details
- Developer
- NEXTDC
- Customer
- To come
- Status
- Design and town planning
- Total capacity
- 1,680 MW
- Actual utilisation
- 840 MW
- Energy source
- Grid
Climate pollution
4.9 Mt CO₂-e / yr
That’s like 1.8 million cars on the road for a whole year.
Share of 2035 target
2.7%
From one project, every year connected to the grid.
-
Rank 5 Beetaloo Digital Climate pollution: 3.5 Mt/yr Same as 1.3M cars
Weddell, Northern Territory
Beetaloo Digital
The project: Beetaloo Digital, a subsidiary of gas corporation Beetaloo Energy, has secured exclusive rights to a 185-hectare site about 30 kilometres (km) from Darwin for a gas-powered data centre development.
Energy: Beetaloo Digital plans to build 2 GW of on-site gas generation that would burn gas piped from Beetaloo Energy’s operations in the Beetaloo Basin (Beetaloo Digital 2026a).
Water: Beetaloo Digital is investigating using closed-loop liquid cooling to minimise water use (Beetaloo Digital 2026b).
Location
Weddell, Northern Territory
Site details
- Developer
- Beetaloo Digital
- Customer
- To come
- Status
- Early development
- Total capacity
- 2,000 MW
- Actual utilisation
- 1,000 MW
- Energy source
- Off-grid gas
Climate pollution
3.5 Mt CO₂-e / yr
That’s like 1.3 million cars on the road for a whole year.
Share of 2035 target
1.9%
From one project, every year running on gas.
-
Rank 6 Hunter Valley AI Training Campus Climate pollution: 3.1 Mt/yr Same as 1.1M cars
Hunter Valley, NSW
Hunter Valley AI Training Campus
The project: Hunter Valley AI Training Campus is a proposed facility up to 1 GW in size in the Hunter Valley designed to make the most of the region’s existing transmission. The site is next to the Redbank Power Station in Warkworth (Voltic DC 2026).
Energy: The facility would connect to the grid. However, Redbank’s owner Verdant Earth Technologies wants to convert the old coal power station to instead burn biomass – including “invasive native species” – to generate energy. The NSW Independent Planning Commission rejected the plan in 2025 based on potential environmental impacts (NSW IPC 2025). If it goes ahead, Voltic says it will explore power supply deals with Verdant (Voltic DC 2026).
Water: The project would have access to water straight from the Hunter River.
Location
Hunter Valley, NSW
Site details
- Developer
- Voltic DC
- Customer
- To come
- Status
- Early development
- Total capacity
- 1,300 MW
- Actual utilisation
- 650 MW
- Energy source
- Grid
Climate pollution
3.1 Mt CO₂-e / yr
That’s like 1.1 million cars on the road for a whole year.
Share of 2035 target
1.7%
From one project, every year connected to the grid.
-
Rank 7 Mayfield Energy Precinct Climate pollution: 3.1 Mt/yr Same as 1.1M cars
Hunter Valley, NSW
Mayfield Energy Precinct
The project: The Mayfield Energy Precinct is a joint data centre campus proposal for up to 1 GW of IT capacity in the Hunter Valley from coal mining company Malabar Resources and Akaysha Energy. The facility would be co-located with Malabar’s mining operations.
Energy: The data centre would draw power from the grid and include a grid-connected battery of up to 2 GW / 8 GWh.
Water: No public commitments have been made on water use. An environmental impact statement is expected in the first half of 2027 (Akaysha Energy 2026).
Location
Hunter Valley, NSW
Site details
- Developer
- Malabar Resources and Akaysha Energy
- Customer
- To come
- Status
- Early development
- Total capacity
- 1,300 MW
- Actual utilisation
- 650 MW
- Energy source
- Grid
Climate pollution
3.1 Mt CO₂-e / yr
That’s like 1.1 million cars on the road for a whole year.
Share of 2035 target
1.7%
From one project, every year connected to the grid.
-
Rank 8 Mamre Road Data Centre Climate pollution: 2.8 Mt/yr Same as 1.1M cars
Western Sydney, NSW
Mamre Road Data Centre
The project: The Mamre Road Data Centre, on a 52-hectare site in Western Sydney, would have a total maximum power demand of 1.2 GW and comprise six separate four-storey buildings, 936 cooling units, 852 diesel back-up generators, and 14.4 million litres of diesel storage (NSW Government 2026). Until recently, this was the largest data centre proposal in the country – and one of the largest in the world – but it has now been surpassed by several others.
Energy: The developer has indicated that it will match its demand with renewable generation through contracts and certificates, though no commitments to bring on new renewable generation and storage have been made (E-Lab consulting 2026).
Water: The Mamre Road facility plans to use air cooling technology, meaning no water will be used for cooling. A small amount of water will be needed for on-site plumbing, for example in bathrooms (E-Lab consulting 2026).
Location
Western Sydney, NSW
Site details
- Developer
- To come
- Customer
- To come
- Status
- Planning assessment
- Total capacity
- 1,200 MW
- Actual utilisation
- 600 MW
- Energy source
- Grid
Climate pollution
2.8 Mt CO₂-e / yr
That’s like 1.1 million cars on the road for a whole year.
Share of 2035 target
1.5%
From one project, every year connected to the grid.
-
Rank 9 Southern Highlands Data Campus Climate pollution: 1.2 Mt/yr Same as 0.4M cars
Moss Vale, NSW
Southern Highlands Data Campus
The project: Sydney company Cloud Carrier is planning a data centre campus on a 67-hectare site in the Southern Highlands.
Energy: Cloud Carrier is seeking to build three gas power stations with a combined capacity of 703 MW to run its data centre campus. The largest, at 673 MW, needs state approval. The developer is appealing the Wingecarribee Shire Council’s refusal of a smaller 16 MW gas power station in the NSW Land and Environment Court (Rushforth 2026).
Water: Cloud Carrier plans to install on-site water harvesting systems (Cloud Carrier 2026).
Location
Moss Vale, NSW
Site details
- Developer
- Cloud Carrier
- Customer
- To come
- Status
- Planning assessment
- Total capacity
- 673 MW
- Actual utilisation
- 336.5 MW
- Energy source
- Off-grid gas
Climate pollution
1.2 Mt CO₂-e / yr
That’s like 430,000 cars on the road for a whole year.
Share of 2035 target
0.7%
From one project, every year running on gas.
-
Total pollution Climate pollution: 39.7 Mt/yr Same as 14.7M cars
Without renewables and storage that matches demand, all of these data centre proposals could add 39.7 million tonnes of pollution a year by 2035. This is:
- Almost as much as Australia’s three most polluting coal power stations, combined, emit every year: Loy Yang A, Eraring and Bayswater (42.9 Mt in 2024-25; Clean Energy Regulator 2026b)
- One-fifth of the pollution Australia can emit in 2035 if we were to successfully cut pollution by 70%, which would help protect us against worsening fires, heat and floods that are already harming Australians.
And it’s not just climate pollution
Without new clean energy, data centres mean price pain
Data centres compete with homes and businesses for the same electricity. When their demand isn’t matched with new renewables, coal and gas plants run harder for longer – and prices go up for everyone.
+20%
Expected wholesale electricity price rise due to data centre demand in 2035
Coal and gas powered data centres could push up your power bills
Baringa and Clean Energy Finance Corporation 2025
Data centres can also use heaps of water
More pressure on water supplies in a hotter, drier climate
As climate change makes droughts hotter and drier in many parts of Australia, and water supplies become less certain in the same regions data centres are being proposed and built, the industry could put further strain on water resources.
These risks can be reduced: with mandatory rules that require data centres to use water efficiently and avoid drawing on fresh water supplies, we can protect these essential resources.
18,800
Olympic swimming pools of water a year in 2035
Climate Council estimates based on assumptions in Mandala and Data Centres Australia’s report Data Centres as Enabling Infrastructure. This applies Mandala’s calculated average WUE for Australian data centres of 1.8 and average PUE of 1.3 to AEMO’s forecast energy consumption of 34 TWh in 2035-36. This assumes there is no improvement in data centre water efficiency between now and 2035-36.
It doesn’t have to be this way
Done right, data centres can build on our clean energy progress
The Australian Government should make its direction clear now, so communities and industries know what to expect.
With strong rules
100% +
New renewables and storage
Every large data centre brings its own new wind, solar and batteries, so we avoid further rises in pollution or power bills.
With weak rules
39.7 million tonnes
Of climate pollution every year
From these nine proposals, drawing on a grid still full of coal and gas, or burning gas on site – contributing to worsening fires, floods and heatwaves in Australia. They would also materially push up power prices.
The ask
The Government is promising to protect Australian communities from the impacts of unchecked data centre growth
To make good on that promise, the law must require:
-
At least 100% new renewables and storage
Every new data centre and its customers match no less than 100% of their energy use with genuinely new renewable power and storage.
-
Built within three years
New renewable generation and storage built within three years, with penalties for non-compliance.
-
No off-grid gas
Close the door on gas as a primary power source, including while data centres set up new renewable energy.
-
Save water and energy
Best-practice water and energy efficiency, and strict limits on drawing on fresh water supplies.
-
Rules for every project
Make the rules cover every new data centre and its customers, everywhere in Australia, including those already in the pipeline.
Join us in telling the Federal Government to get data centres rules right